News
2023
- 13.06.23
A new digital beginning: The Tyra field can now be remote controlled from shore
Esbjerg, 13 June 2023 – Today, TotalEnergies is starting up the new established Tyra onshore control room – a crucial milestone for the whole offshore industry and a visible sign that the redevelopment of Denmark’s largest gas field soon comes to an end.
- 09.02.23
First well reinstatement on Tyra II is complete
Esbjerg, 9 February 2023 – This week the well campaign has started, and the first refurnished well equipment has been successfully installed on the new Tyra II marking yet another important milestone in the final phase of the Tyra Redevelopment project.
2022
- 13.12.22
The old Tyra is now history – 98.5% reused or recycled
Esbjerg, 13 December 2022 – The largest recycling project of offshore installations in Denmark’s history has successfully completed. After 2.5 years of dismantling work on the old platforms and structures from the Tyra field, 98.5% of the material has now been reused and recycled.
- 10.10.22
Last connecting bridge touched down: Tyra II now has its final shape
Esbjerg, 10 October 2022 – The last remaining piece of Tyra II puzzle was lifted into its final position. The world’s largest crane Sleipnir will soon leave the Tyra field after a successful installation campaign.
- 04.10.22
Final Tyra-topside lift breaks world record
Esbjerg, 4 October 2022 – Today at 8:27, the biggest Tyra II topside touched safely down on the last remaining bare jacket at the Tyra field. The lift of the 17,000 tons heavy process module broke a world record as the heaviest crane lift ever undertaken at sea.
- 01.09.22
New Tyra process module sets off on 8,700 nautical miles journey
TotalEnergies EP Denmark and its Danish Underground Consortium partners Noreco and Nordsøfonden are pleased to announce the successful sail away of the new Tyra II process module.
- 03.08.22
Restart of production from the Tyra field delayed to the winter season 2023/24
First gas from the redeveloped Tyra field will be delayed to the winter season 2023/24 due to manufacturing and supply chain disruptions.
- 12.04.22
The Tyra II puzzle is almost completed
Esbjerg, 12 April 2022: TotalEnergies EP Denmark and its Danish Underground Consortium partners Noreco and Nordsøfonden are pleased to announce the successful completion of this spring’s installation campaign of Tyra II in the Danish North Sea.
- 03.04.22
The installation of Tyra II goes into the next round
Esbjerg, 3 April 2022: TotalEnergies EP Denmark and its Danish Underground Consortium partners Noreco and Nordsøfonden are pleased to announce the successful start of this spring’s installation campaign at the Tyra field.
- 16.03.22
New Tyra II utility and living quarters are en route to the North Sea
Esbjerg, 16 March 2022: TotalEnergies EP Denmark and its Danish Underground Consortium partners Noreco and Nordsøfonden are pleased to announce the successful sail away of the new Tyra II utility and living quarters.